Quick Search

Park contacts

 Will Walpole

Contracts and Services Manager

020 8693 8635 (office)
07940 457592 (mobile)

This email address is being protected from spambots. You need JavaScript enabled to view it. 

 

Robert Roach

Contracts and Services Officer

020 8693 8635

This email address is being protected from spambots. You need JavaScript enabled to view it. 

 

Ciro deLucia

Park Liaison Officer
07908 767784

 Southwark Wardens

020 7740 1665 (weekends)

 

 Dulwich Park Friends

07967 000546 (mobile)

This email address is being protected from spambots. You need JavaScript enabled to view it.

 

 

Eastern Lawns
Work involving the installation of an underground water storage tank is now complete. The area will now also be reseeded and protected to ensure the grass thrives and is ready for use.
Francis Peek Centre
Construction of the flood bunds in the Western Lawn area has been completed. Here too, work will now begin to ensure the grass is returned to the same state as it was before our work started.
Southern Carriage Drive
The Drive is due to reopen by 7th November and work is progressing well in order to meet this deadline.
The work on this route was essential in order to raise the level to that of the height of the flood defences.
Western Lawns and Horse Drive
Flood update 2nd imageOur work at the site of the second underground water storage tank, which currently involves connecting drainage from the tank to the sewer network, will be completed by 5th December. When our teams have finished, the site will be reseeded and fenced for protection as has been done with our other completed work areas.
Work on the underground water storage tank in Dulwich Park is due to end on 5th December.
The Boating Lake
Work on the footpath by the Boating Lake will be completed by 12th December. As a main route through the park it provides access to the cafe, we will ensure clear signs direct people around our work area. This work is necessary to raise the level of the footpath in line with the flood defences. Belair Park
All of our work in the park will be completed by 21st November. During the process of this project we have constructed flood defence bunds around the playing fields and play area and to the west of the lake. A wetland meadow and new footpath completing a circular route around the lake has also been constructed.
All that remains now is to ensure that the grass is re-established in the areas we have been working. It will remain protected by fencing to ensure it is given the best chance to thrive during the winter months'.